Compañía Cervecera de Zacatecas

July 1994 – January 1996
Electrical Installation of the 1st stage engine room for air compressors, ammonia, CO₂, cooling towers.
August 1995 – March 1996
-Electrical assembly in water recover plant for bottling.
May 1996 – August 1997
-Electrical installation of brewing house, reception and milling grain (first stage).
October 1997
-Mounting of main board METAL-CLAD.
December 1997
-Pipeline supply for Z boards of brewing house, reception and milling grain (second stage).
August 1997 – July 1998
-Electrical installation of brewing house, reception and milling grain (second stage).
March 1998 – November 1999
-Electrical installation of engine room (second stage).
March 1999 – November 1999
-Power and control installation for ammonia screw compressor of 1000 H.P.
September 1999 – April 2000
-Electrical installation of engine room (third stage).
June 2000 – January 2001
Electrical installation of silos and grits warehouse (third stage).
March 2001 – April 2002
-Electrical installation for air, ammonia and carbonic gas systems of engine room (fourth stage).
April 2001 – October 2001
-Electrical work on re-pumping system and four water wells.
October 2001 – April 2002
-Electrical installation of four external water wells.
April 2002 – February 2003
-Enlargement of enginge room.